3 people can build 2 walls in 4 days. how many days would it take 1 person to build 3 walls?
Share
3 people can build 2 walls in 4 days. how many days would it take 1 person to build 3 walls?
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Answer: It would take 6 days