9. If an air-conditioning system is not completed by the agreed upon date, the
contractor pays a penalty of P5,000 for the first day that is overdue, P6,000
for the second day, P7,000 for the third day. If the system is completed 15
days late, then what will be the penalty for day 15?
A. P19,000 B. P20,000 C. P21,000
D. P22,000
Share
Answer:
A.P19,000
Explanation
day. cost of penalty
1. P5,000
2. P6,000
3. P7,000
4. P8,000
5. P9,000
6. P10,000
7. P11,000
8. P12,000
9. P13,000
10. P14,000
11. P15,000
12. P16,000
13. P17,000
14. P18,000
15. P19,000