Analyze and Solve. And put the type of proportion (direct, inverse or partitive)
It takes 6 days for 4 workers to finish a certain job. How many days will it take to finish the same job if only 3 workers will do the job?
patulong po with solution sana
Share
Answer:
7 days
yan na po ungsolution